Survey work starts ahead of North Devon Link Road scheme

North Devon Link Road trafficNorth Devon Link Road

Posted on: 1 April 2019

Survey work is starting on a section of the North Devon Link Road this week, ahead of the planned major road widening scheme.

Devon County Council granted planning permission in February for widening of the A361 between Filleigh and Portmore, and the authority is now carrying out preparatory work ahead of the scheme getting underway in 2021.

Investigative work is planned to be carried out at different periods for the rest of this year, some of which may have an impact on traffic.

Today (Monday 1 April) and tomorrow (Tuesday 2 April), samples of the road are being taken in various locations between Filleigh and Portmore.

Temporary traffic lights will be used while short lane closures are in place for brief periods while the road material samples are taken. This work will be carried out outside of peak times, with traffic lights only in operation from 9:30am-3:30pm.

Road surface condition surveys will also be carried out later this spring, which will involve a slow-moving vehicle scanning the road surface for up to three days – but again only between 9:30am and 3:30pm. The slow speed of the vehicle means that mobile traffic lights will need to control traffic around it.

From late April to late July, surveys will be carried out on the land next to the road. Surveyors will be working up to the edge of the road and for their safety and the safety of the travelling public, an area at the edge of the traffic lane will be coned off and a speed limit of 40mph will be introduced. The length of road under these restrictions will be no more than one mile at a time.

Utility services such as water and electricity supplies will be relocated throughout this summer, but it’s not currently thought this will impact on traffic.

Later this year, in the autumn and winter, lots of planting will be undertaken at the side of the road to screen the road from surrounding viewpoints and also to establish ecological habitats. These planting works will also not impact on road traffic.

When further information is available it will be published on the scheme website.

Posted in: Business and Economy | DCC Homepage | Environment